Bid Opportunities

BP Name Scope Description & Delineation Package Issued for Bid (Forecasted) Status
Structural Steel Fabrication & Erection Structural Steel Fabrication & Erection 2/13/2023 Package Awarded
Building Concrete/Foundations Production Building – Remaining Building Foundations 3/10/2023 Package Awarded
Exterior Metal Panels & Louvers Exterior Metal Panels & Louvers 3/10/2023 Package Awarded
Mechanical – Package 1 Mechanical (Pkg 1: HVAC & Plumbing, Pkg 2: All Misc. Bldgs, Pkg 3: Process Piping/Systems) 5/5/2023 Package Awarded
Mechanical – Package 2 5/5/2023 Package Awarded
Mechanical – Package 3 5/5/2023 Package Awarded
Roofing Roofing 3/10/2023 Package Awarded
Underslab Conduit Underslab Conduit 3/24/2023 Package Awarded
Temporary Site Power Temporary Site Power 3/24/2023 Package Awarded
Elevators Elevators 3/31/2023 Package Awarded
Fire Suppression Fire Suppression 5/4/2023 Package Awarded
Electrical – Package 1 Electrical (Pkg 1: High Voltage, Pkg 2: Distribution, Pkg 3: Site Power, Aux Buildings) 5/5/2023 Package Awarded
Electrical – Package 2 5/5/2023 Package Awarded
Building Concrete/Foundations Building Concrete/Foundations – SOG/SOD 4/25/2023 Package Awarded
OH Doors & Dock Equipment OH Doors & Dock Equipment 4/24/2023 Package Awarded
Underslab Plumbing & Piping Underslab Plumbing & Piping 5/3/2023 Package Awarded
Sealant, Caulking in SOG Sealant, Caulking in SOG 5/5/2023 Package Awarded
Exterior Framing & Blocking Exterior Framing & Blocking 5/4/2023 Package Awarded
Exterior Doors, Frames, Hardware Exterior Doors, Frames, Hardware 5/4/2023 Package Awarded
Glass & Glazing Glass & Glazing 4/28/2023 Package Awarded
Partial Misc. Metals Partial Misc. Metals – External 5/12/2023 Package Awarded
BMS & Controls BMS & Controls 5/17/2023 Package Awarded
Masonry Masonry 6/23/2023 Package Awarded
Interior OH Doors Interior Overhead Doors 6/23/2023 Package Awarded
Metal Stud & Drywall (Level 1) Drywall (Production Level 1) 6/23/2023 Package Awarded
Metal Stud & Drywall (Level 2) Drywall (Production Level 2) 6/23/2023 Package Awarded
Doors, Frames, Hardware (Interior) Interior Doors, Frames, Hardware 6/23/2023 Package Awarded
Metal Buildings (Support Buildings) Pre-Engineered Metal Buildings 7/19/2023 Package Awarded
Resinous Flooring Resinous Flooring 6/23/2023 Package Awarded
Dry / Clean Rooms Dry / Clean Rooms 6/28/2023 Package Awarded
Glass & Glazing (Interior) Interior Glass and Glazing 7/14/2023 Pending Award
Fire Caulking Fire Caulking 8/3/2023 Package Awarded
General Trades General Trades 8/31/2023 Package Awarded
Painting & Acoustical Caulking Painting & Acoustical Caulking 8/17/2023 Package Awarded
Tiling Wall & Floor Tile 7/14/2023 Scope Removed from Project
Rubber Base Rubber Base between wall and floor. Package formerly named VCT & Carpet 1/31/2024 Package Awarded
Miscellaneous Steel (Interior) Interior Misc Metals 7/28/2023 Package Awarded
Support Building Structural Steel Support Building Structural Steel 8/14/2023 Package Awarded
Fire Alarm Fire Alarm 8/24/2023 Package Awarded
Telecommunications/Technology Structured Cabling 10/18/2023 Package Awarded
Security Systems Electronic Security 10/18/2023 Package Awarded
Food Service Equipment Food Service Equipment TBD Scope Removed from Project
Support Building Interior Fitout Auxillary Building Contractors TBD Not Issued to Bid
Landscaping Landscaping TBD Not Issued to Bid
Site Fencing Site Fencing 5/16/2024 Bid Leveling
Site Concrete Paving Site Concrete Paving 5/16/2024 Bid Leveling
Final Clean Construction Final Cleaning TBD Not Issued to Bid